SIPS Extension, Scarcroft Primary School, York
The architect was looking for a light weight method of construction which would provide a good substrate for fixing external Cedar Boarding and also providing a fast track method of construction. The Kingspan TEK Building System met all these criteria and also provides the low āUā values required to conform to the building regulations.
Development factfile
Client: York City Council
Contractor: William Birch & Sons Ltd, York
Architect: Atkins, Century Way, Leeds
SIPS Started: February 2006
SIPS Completed: July 2006
INTERESTING FACT: SIPS construction took only five days on site !
The materials
Foundation: Block and Beam
Walls and roof: Kingspan TEK Building System
Outer walls: 25mm Thick Cedar Boards
Roof Tiles: Follansbee TCS Longstrip
Heating: Underfloor