SIPS Stable Block, Addingham

Using SIPs for this project may initially seem a bit over the top but in fact saved many hours on site in the middle of winter and shows how versatile SIPs are!


Development factfile

Client: J.Clay & Sons (Livestock)
Contractor: Clays of Addingham Limited
Architect: John & Jennifer Wharton, Carleton, Skipton
SIPS Started: Tuesday 6th January 2009
SIPS Completed: Friday 9th January 2009
Project Address: Main Street, Addingham
INTERESTING FACT: The SIPs went up in four days using a contractor who had never installed the product before. He was particularly impressed with how easy it was to fasten the cladding and Yorkshire boarding to the panel.

The materials

Foundation: Concrete Slab
Walls and roof: Kingspan TEK Building System (SIPs)
Outer walls: Tanalized Timber - Yorkshire Boarding
Roof Tiles: Plastic Coated Metal Roof Sheets


Request a Quotation