SIPs Chalet by the Sea

When our client, Mr & Mrs Wood, required a quick & efficient build SIPs were the obvious way to go. The SIPs shell meant coordinating the project was relatively easy and it resulted in a build time of less than three months.


Development factfile

Client: Mr & Mrs M.Wood
Contractor: Managed by Client
Architect: Light & Berry
SIPS Started: 3.10.11
SIPS Completed: 8.10.11
Project Address: Ferry Road, Hayling Island, Portsmouth
INTERESTING FACT: The Structural Insulated Panels were erected in less than a week making a virtually watertight building for the 1st fix to be started.

The materials

Foundation: Strip foundations/beam & block floor
Walls and roof: The Kingspan TEK Building System
Outer walls: Cement Board & Render
Roof Tiles: Tata Urban Standing Seam Steel Roof
Gutters: Integral
Heating: Air ducting