SIPS Extension, Scarcroft Primary School, York

The architect was looking for a light weight method of construction which would provide a good substrate for fixing external Cedar Boarding and also providing a fast track method of construction. The Kingspan TEK Building System met all these criteria and also provides the low ā€œUā€ values required to conform to the building regulations.


Development factfile

Client: York City Council
Contractor: William Birch & Sons Ltd, York
Architect: Atkins, Century Way, Leeds
SIPS Started: February 2006
SIPS Completed: July 2006
INTERESTING FACT: SIPS construction took only five days on site !

The materials

Foundation: Block and Beam
Walls and roof: Kingspan TEK Building System
Outer walls: 25mm Thick Cedar Boards
Roof Tiles: Follansbee TCS Longstrip
Heating: Underfloor