Raising the Roof using SIPs
The client had purchased a bungalow on a fantastic plot, the architects brief was to add an additional floor to achieve a low energy four bedroomed family home. The lightweight nature of SIPs and the speed of erection has allowed the architect to achieve his goal.
Development factfile
Client: Mr & Mrs Reyard
Contractor: P.S. Armstrong, Skipton T: 07740 821519
Architect: Mark Phillip, Skipton
SIPS Started: 11.9.09
SIPS Completed: 19.9.09
Project Address: 'Larkrise', Threshfield, Near Skipton
INTERESTING FACT: The total time period for the whole contract should be no more than five months. SIPs have played a great part in achieving this short build period, but a great deal of credit must go down to the planning and organisation of the main contractor, Paul Armstrong, who now has the experience of working on over four SIPs contracts with SIPS@Clays.
The materials
Foundation: Existing ground floor block walls
Walls and roof: The Kingspan TEK Building System (SIPs)
Outer walls: Traditional Yorkshire Dales Stone to match the existing.
Roof Tiles: Stone Slates
Heating: Underfloor heating.